The Department of
Ecology issued an official notice of the upcoming March 20, 2012 “pre-scoping”
meeting – more on the details in a minute.
But first, let’s
recognize that this “pre-scoping” session is something of an anniversary. Well, not really an anniversary. An inverted anniversary, I guess. Or a non-anniversary.
Perhaps we could
view it as a non-event.
You see, the schedule that the project applicant and all the agencies put together back in November 2010(see pages 108 and 122) showed that the Final Environmental Impact Statement would be completed on March 14, 2012. That's -- right about now!
And the EIS was supposed to be completed five days before March
19, 2012, when the coal terminal applications
are likely to be turned into Whatcom County.
On March 20, there will be a “pre-scoping” session. “Pre-scoping” means that the Environmental Impact Statement process hasn’t (officially) begun yet – and that’s six days after its projected date of completion.
If time were really
telescoped like that, dinosaurs and humans would, in fact, be able to exist at
the same time. (That’s the significance
of the picture, by the way. Along with
the fact that I really like dinosaurs.)
Now, we’ll probably
hear some grumble-grumble-grumbling that
this delayed process shows that red tape just gets in the way, grumble
grumble.
Red tape like when
the County required the coal terminal applications to resemble the current
proposal, not the proposal back in the 1990s.
Red tape like holding
up “progress” on the project – when “progress” meant bulldozing roads, destroying
archeological midden sites, and filling wetlands without the necessary permits.
Red tape like the
letters pouring in from citizens in Whatcom County and all along the train route,
telling the agencies that their lives and their concerns matter, too.
I think that the
original schedule is very telling. It showed
that the agencies themselves weren’t even aware of the magnitude of this
project, because nobody would have put together a schedule like that if they had
thought the project through.
And now we have the
opportunity to start telling the agencies that they need to think the project
through, and what that means to us.
Here’s the press
release for the March 20 “pre-scoping” meeting:
Washington
Department of Ecology news
FOR IMMEDIATE
RELEASE – March 5, 2012
12-076
Meeting set to inform public about environmental review process for proposed Cherry Point terminal
BELLINGHAM – People interested in the
upcoming process to review potential environmental impacts from the proposed
Gateway Pacific Terminal and a related railroad project are invited to an
informational meeting.
Meeting details:
Project: Proposed Gateway Pacific
Terminal at Cherry Point, north Puget Sound
What: Information meeting on
environmental review processWhen: 6 – 8 p.m. Tuesday, March 20, 2012
Where: Bellingham High School theater, 2020 Cornwall Ave.
Representatives from Whatcom County and
the Washington Department of Ecology (Ecology) will outline the environmental
review process and answer questions about it. A representative from the U.S.
Army Corps of Engineers (Corps) will be on hand to answer questions about the
Corps permitting process and federal requirements.
Whatcom County, Ecology and the Corps
have agreed to coordinate the environmental impact statement (EIS) process
under state and federal environmental laws.
The purpose of the meeting is to
familiarize people with the upcoming environmental review process. Speakers
will explain several opportunities people will have to provide formal input at
different stages. The first of these will occur in late spring or summer this
year.
An EIS reports on the potential impacts a
proposed project would have on the natural and social environment. Once the
impacts are identified, it outlines “mitigation,” measures intended to offset
impacts. The EIS also evaluates alternatives, and their potential impacts, to
the project or portions of it. Agencies that issue permits can use this
information to determine whether to approve the project, and if approved, to
set conditions to prevent or mitigate impacts.
The meeting program will outline the
upcoming EIS process, including these key points, with approximate dates:
• Scoping: This
summer the agencies will seek public comment, including community meetings,
through “scoping,” a process the agencies use to determine which potential
environmental impacts the EIS should assess. The co-lead agencies will issue
notices for times and locations of scoping meetings.
• Draft EIS: The
agencies, aided by their consultant, will research potential impacts,
alternatives, and mitigation measures, and present the results of these studies
in a draft EIS, expected in 2013.
• Public comment on
draft EIS: The agencies will invite the public to review the draft EIS and to
make comments. This can include workshops, meetings and hearings to explain the
EIS and to receive public comments. This period will most likely occur in late
2013 or in 2014.
• Final EIS: The
agencies make changes to the draft EIS based on comments received and issue a
final version.
• Permitting:
Several local, state and federal agencies will use information from the EIS to
help make permit decisions. Each permit has its own process for public review
and input before becoming final. If a permit is issued, the issuing agency may
use mitigation identified in the EIS to help set special conditions or
requirements.
Pacific International Terminals, a
subsidiary of SSA Marine Inc. (SSA), proposes to build and operate the Gateway
Pacific Terminal at Cherry Point in north Puget Sound, between Ferndale and
Blaine. The terminal would provide storage and handling of exported and
imported dry bulk commodities, including coal, grain, iron ore, salts and
alumina. BNSF Railway Inc. proposes to add rail facilities and install a second
track along the six-mile Custer Spur.
### Media Contacts:
Tyler Schroeder, Whatcom County
Planning Supervisor, 360-676-6907, tschroed@co.whatcom.wa.us
<mailto:tschroed@co.whatcom.wa.us>
Larry Altose, Ecology media relations,
206-920-2600, larry.altose@ecy.wa.gov <mailto:larry.altose@ecy.wa.gov>
Katie Skipper, Ecology media relations,
360-715-5205, katie.skipper@ecy.wa.gov
<mailto:katie.skipper@ecy.wa.gov>
Patricia Graesser 206-764-3760, Corps
of Engineers media relations, Patricia.graesser@us.army.mil
<mailto:Patricia.graesser@us.army.mil>
For more
information:
Ecology's Gateway Pacific Terminal page
(www.ecy.wa.gov/geographic/gatewaypacific
<http://www.ecy.wa.gov/geographic/gatewaypacific> )
Whatcom County's Gateway Pacific
Terminal page (www.co.whatcom.wa.us/pds/plan/current/gpt-ssa/index.jsp
<http://www.co.whatcom.wa.us/pds/plan/current/gpt-ssa/index.jsp> )
Washington Office of Regulatory
Assistance (http://iprmt.ora.wa.gov/ <http://iprmt.ora.wa.gov/> )
requires registration
U.S. Army Corps of Engineers, Seattle
District (www.nws.usace.army.mil <http://www.nws.usace.army.mil> )
Ecology’s website:
http://www.ecy.wa.gov <http://www.ecy.wa.gov>
Ecology’s social
media: http://www.ecy.wa.gov/about/newmedia.html
<http://www.ecy.wa.gov/about/newmedia.html>
Why, thank you Jean, for this breaking news. I guess March 20th it is.
ReplyDeleteLet the subsidy begin (continue)!
Well, heck, we already broke the news, right? The rewards of the nerdy habit of reading primary documents. Something of which you are often guilty yourself, Mr. Stalheim.
DeleteThank you Jean. See you and David at the party on the 20th if not before!
ReplyDeleteShould we all bring noise makers? Party hats? :)
ReplyDeleteJean, the only bone I would pick with you is that I don't think the ridulous initial scheduling was because they weren't thinking, but because, in early 2011, they were thinking if SSA said it, it must be so (sort of the same, but a little different). SSA said (I'm paraphrasing, but only a little), "We don't need no stinking' Shoreline Substantial Development Permit. Got that in '97." And the MAP Team didn't put no stinkin' SSDP on the schedule. SSA said (again, paraphrasing), "All this permit s**t will be over in a matter of months," and the schedule reflected ... a matter of months.
ReplyDeleteThere will be more than one party on March 20th. Get your dancing shoes on 'cause the party is about to start.
ReplyDelete